When you need it
Use this record when an employer or another authorized party transfers possession of all or part of a construction site, especially where boundaries, existing conditions, or shared access require explicit agreement.
AI tools and documents for engineering and project management.
Record the area handed over for construction, its condition, access, constraints and responsibilities.
How to use this templateThis Word template contains prepared headings, tables, project fields and completion notes. Add your information, review the completed document and remove the notes before issue.
The form prepares a separate brief; it does not fill the Word or Excel file.
Read product descriptions in your language. The Word and Excel template files are in English.
Only selected pages are shown. This is not the complete template. The full editable Word or Excel file is supplied with purchase.
Learning
Use this record when an employer or another authorized party transfers possession of all or part of a construction site, especially where boundaries, existing conditions, or shared access require explicit agreement.
It establishes what area and physical information were actually transferred, in what condition, and with which reservations, supporting mobilization decisions and later assessment of access constraints or pre-existing conditions.
Client and contractor site representatives normally prepare the record together, supported by survey, utilities, safety, and property specialists as relevant. Transfer and receipt are signed only by roles authorized under project arrangements.
Signing for full possession when the attached plan excludes essential access areas hides a constraint that can immediately affect mobilization and sequencing.
Illustrative example: a hospital extension receives only its northern work area because an ambulance route remains operational. The possession record attaches a marked plan, records shared utility access and existing pavement damage, and identifies restrictions. The contractor mobilizes within the transferred boundary and revises delivery routing.
Confirm the adopted edition, local amendments, National Annex where relevant, and contract requirements.