This Word template contains prepared headings, tables, project fields and completion notes. Add your information, review the completed document and remove the notes before issue.
The form prepares a separate brief; it does not fill the Word or Excel file.
Read product descriptions in your language. The Word and Excel template files are in English.
Selected page preview · DOCX
Only selected pages are shown. This is not the complete template. The full editable Word or Excel file is supplied with purchase.
Learning
How to use this template
When you need it
Use this record when takeover of identified works must be documented under the applicable NEC contract, including situations where the relationship between use, takeover, Completion, and remaining work requires careful clarification.
What it helps you decide
It identifies what has been taken over and the actual contractual basis, helping delivery and operations teams coordinate responsibilities without assuming that takeover and Completion always represent the same event or decision.
How to complete it
Check Certificate and contract particulars and define Scope certified and exclusions using the actual takeover provisions, affected works, and relevant event records.
Reference Evidence supporting the milestone and list Outstanding items and reservations, distinguishing factual use or occupation from the contract's required takeover assessment.
State the Certification statement and contractual effect without conflating takeover with Completion, then attach related records and document Authorized issue and receipt.
Who prepares and reviews it
The role responsible under the actual NEC agreement prepares or issues the record with client, contractor, operations, and contract-administration input. Reviewers confirm the relevant form, amendments, boundaries, and authorized communication arrangements.
A mistake to avoid
Copying the Completion certificate unchanged can conceal the different factual event, scope boundary, or contractual treatment relevant to takeover under the actual agreement.
Illustrative example
Illustrative example: an employer begins using a completed access road while adjacent NEC works continue. The record identifies the road boundary, actual use evidence, and relevant contract provisions. The designated role records the applicable takeover position and clarifies continuing interfaces with the remaining construction area.