When you need it
Prepare this quotation when the applicable NEC compensation-event process calls for a priced and programme-based assessment of a defined event, using the actual contract's instructions, assumptions, and assessment rules.
AI tools and documents for engineering and project management.
Present a compensation-event quotation with defined cost and programme effects under the selected NEC contract.
How to use this templateThis Word template contains prepared headings, tables, project fields and completion notes. Add your information, review the completed document and remove the notes before issue.
The form prepares a separate brief; it does not fill the Word or Excel file.
Read product descriptions in your language. The Word and Excel template files are in English.
Only selected pages are shown. This is not the complete template. The full editable Word or Excel file is supplied with purchase.
Learning
Prepare this quotation when the applicable NEC compensation-event process calls for a priced and programme-based assessment of a defined event, using the actual contract's instructions, assumptions, and assessment rules.
It brings scope, cost components, programme effects, and assumptions together so the recipient can assess a coherent proposal rather than disconnected estimates or unqualified records of actual expenditure.
The contractor's commercial lead usually coordinates estimating, planning, engineering, and delivery inputs. The authorized contract role reviews the quotation under the applicable NEC form, with specialist support for disputed assumptions or complex effects.
Treating every incurred cost as recoverable without checking the contract's assessment basis can overstate the quotation and undermine otherwise supported elements.
Illustrative example: a changed pipe corridor requires temporary supports and a revised installation sequence. The quotation references the event notification, separates recorded preparatory work from forecast activities, and attaches a programme assessment. The reviewer requests clarification of crane availability before deciding the quoted consequences.
Confirm the adopted edition, local amendments, National Annex where relevant, and contract requirements.
Prepare project brief