When you need it
Start when a feasibility study begins accumulating assumptions and source material. Update before option reviews and investment gates, particularly when older evidence or new findings may change a material conclusion.
AI tools and documents for engineering and project management.
Trace feasibility assumptions to evidence, decision sensitivity and a plan to resolve important gaps.
How to use this templateThis Excel template contains prepared working sheets and completion notes on a separate sheet. Enter your project data and review the completed workbook before use.
This editable workbook helps you organise project information. Check any included formulas, assumptions and results before use; it does not replace professional review.
The form prepares a separate brief; it does not fill the Word or Excel file.
Read product descriptions in your language. The Word and Excel template files are in English.
Only selected pages are shown. This is not the complete template. The full editable Word or Excel file is supplied with purchase.
Learning
Start when a feasibility study begins accumulating assumptions and source material. Update before option reviews and investment gates, particularly when older evidence or new findings may change a material conclusion.
The register reveals what the feasibility recommendation actually depends on. It directs verification effort toward assumptions capable of changing the decision and prevents repeated estimates from acquiring the appearance of established facts.
The study coordinator maintains entries with technical, market and commercial assumption owners. A reviewer challenges reliability and decision sensitivity; the sponsor decides how unresolved gaps affect the next authorized gate.
Citing the study itself as evidence for an assumption creates circular support and hides that the underlying capacity, cost or demand claim remains unverified.
Illustrative example: a feasibility study assumes an existing substation can supply a new workshop. The register identifies the assumption's source and the cost estimate depending on it. Because a contrary provider response could change the concept, the study lead prioritizes capacity confirmation before recommending the option.
Confirm the adopted edition, local amendments, National Annex where relevant, and contract requirements.