When you need it
Use when a contractor or owner needs to assess alleged loss of productivity. Begin while production and resource records can still be reconciled, before selecting comparison periods or estimating loss.
AI tools and documents for engineering and project management.
Organize comparable production and resource records for assessment of alleged disruption.
How to use this templateThis Excel template contains prepared working sheets and completion notes on a separate sheet. Enter your project data and review the completed workbook before use.
This editable workbook helps you organise project information. Check any included formulas, assumptions and results before use; it does not replace professional review.
The form prepares a separate brief; it does not fill the Word or Excel file.
Read product descriptions in your language. The Word and Excel template files are in English.
Only selected pages are shown. This is not the complete template. The full editable Word or Excel file is supplied with purchase.
Learning
Use when a contractor or owner needs to assess alleged loss of productivity. Begin while production and resource records can still be reconciled, before selecting comparison periods or estimating loss.
The worksheet establishes whether compared work and labour records are genuinely comparable. It distinguishes event-related working conditions from learning, weather, rework or resource changes that may also explain lower output.
A productivity or claims analyst prepares it with trade supervisors, timekeeping staff and planners. A specialist reviewer checks comparability and method; commercial and legal roles assess entitlement and recoverability separately.
Comparing total payroll hours with installed quantities from only one work area produces a distorted productivity measure and may attribute unrelated time to the alleged disruption.
Illustrative example: cable installation output falls during repeated area handovers. The worksheet matches installed quantities with attributable crew hours and records changing access, cable sizes and crew composition. The analyst then decides whether a comparison period can isolate the handover effect sufficiently to support further assessment.
Confirm the adopted edition, local amendments, National Annex where relevant, and contract requirements.