Design Management Plan

Plan design responsibilities, information flow, coordination, reviews and controlled release.

How to use this template

This Word template contains prepared headings, tables, project fields and completion notes. Add your information, review the completed document and remove the notes before issue.

The form prepares a separate brief; it does not fill the Word or Excel file.

Read product descriptions in your language. The Word and Excel template files are in English.

Selected page preview · DOCX

Only selected pages are shown. This is not the complete template. The full editable Word or Excel file is supplied with purchase.

Learning

How to use this template

When you need it

Prepare this plan when multiple disciplines, organizations, or design stages must deliver coordinated information, particularly where approvals, construction interfaces, and changing inputs could disrupt design quality or programme commitments.

What it helps you decide

It explains how design work will be organized, coordinated, reviewed, issued, and changed, allowing participants to manage dependencies and avoid treating isolated discipline completion as readiness for construction or acceptance.

How to complete it

  1. Define Scope, stages and delivery strategy, then assign Roles and responsibilities for inputs, coordination, verification, client decisions, and controlled information issue.
  2. Connect Inputs, deliverables and programme to actual design dependencies, and describe Coordination and interface control for discipline boundaries and construction information needs.
  3. Set Review, verification and change control arrangements, describe Issue, acceptance and records, and track Design risks and outstanding actions through relevant reviews.

Who prepares and reviews it

The design manager usually leads preparation with discipline leads, planners, document control, construction, and client reviewers. Governance establishes who verifies technical work, accepts deliverables, and authorizes changes or issue statuses.

A mistake to avoid

Treating document issue dates as the whole design programme overlooks input dependencies, review periods, interdisciplinary checks, and decisions that determine whether outputs are usable.

Illustrative example

Illustrative example: a process building needs civil, structural, piping, and electrical designs from separate firms. The plan aligns equipment-load inputs with foundation release dates and defines coordination reviews. When vendor loads arrive late, the design manager records the dependency and adjusts the affected release sequence.

Explore the wider topic

Document contents

  • Scope, stages and delivery strategy
  • Roles and responsibilities
  • Inputs, deliverables and programme
  • Coordination and interface control
  • Review, verification and change control
  • Issue, acceptance and records
  • Design risks and outstanding actions

Required inputs

  • Project name, location, company, document number and revision
  • Actual project scope, source records and responsible roles

Practical tools.
Professional judgment.

Confirm the adopted edition, local amendments, National Annex where relevant, and contract requirements.

Prepare project brief