Compare delivery and contracting arrangements against the owner's capability, design maturity and risk allocation.
How to use this templateThis Word template contains prepared headings, tables, project fields and completion notes. Add your information, review the completed document and remove the notes before issue.
The form prepares a separate brief; it does not fill the Word or Excel file.
Read product descriptions in your language. The Word and Excel template files are in English.
Only selected pages are shown. This is not the complete template. The full editable Word or Excel file is supplied with purchase.
Learning
Prepare before choosing the project's delivery and contracting approach. Revisit it if design maturity, owner capability or supplier-market conditions change enough to affect the proposed distribution of responsibilities and risk.
The appraisal tests whether a delivery arrangement fits the owner's actual capabilities and information maturity. It exposes retained interfaces and selection conditions rather than assuming a contract label transfers every management burden.
The project director coordinates engineering, procurement, commercial and operational contributors. Legal advisers review implications of proposed risk allocation; the owner’s authorized governance body selects the approach after considering capability and market evidence.
Choosing a delivery model solely for apparent price certainty can conceal immature scope and owner decisions that remain unresolved regardless of the selected contract form.
Illustrative example: an owner considers a single integrated contractor for an industrial extension while process requirements remain unsettled. The appraisal identifies unresolved owner decisions and market qualifications. Management then decides whether to mature the design first or accept a route with explicitly managed uncertainty.
Confirm the adopted edition, local amendments, National Annex where relevant, and contract requirements.