When you need it
Prepare this submission when an identified contract event has produced asserted time or cost effects that require a substantiated request, following the actual contract's notice and submission arrangements.
AI tools and documents for engineering and project management.
Present a substantiated contractor claim with contract basis, causation, time or cost effects and supporting records.
How to use this templateThis Word template contains prepared headings, tables, project fields and completion notes. Add your information, review the completed document and remove the notes before issue.
The form prepares a separate brief; it does not fill the Word or Excel file.
Read product descriptions in your language. The Word and Excel template files are in English.
Only selected pages are shown. This is not the complete template. The full editable Word or Excel file is supplied with purchase.
Learning
Prepare this submission when an identified contract event has produced asserted time or cost effects that require a substantiated request, following the actual contract's notice and submission arrangements.
It connects the contractual basis, event chronology, causation, programme effect, and quantum, enabling the recipient to assess the requested relief and distinguish evidenced consequences from unsupported assertions or forecasts.
A contract manager typically leads, supported by the planner, quantity surveyor, site team, and relevant technical specialists. Commercial and legal reviewers assess entitlement, while the authorized representative controls formal submission.
A long event narrative without demonstrated critical-path effect or cost causation does not establish the relief requested in the claim summary.
Illustrative example: late access prevents excavation of a pumping station. The contractor records possession correspondence, daily labour records, and programme updates, then demonstrates the affected sequence. The submission requests a substantiated extension and evidenced costs, while identifying a disputed concurrent equipment delay for assessment.
Confirm the adopted edition, local amendments, National Annex where relevant, and contract requirements.
Prepare project brief