When you need it
Prepare this plan before changes begin affecting approved project baselines, or when inconsistent requests and approvals show that scope, cost, schedule, and technical decisions need a clearer shared control process.
AI tools and documents for engineering and project management.
Set the project process for requesting, assessing, deciding and implementing changes.
How to use this templateThis Word template contains prepared headings, tables, project fields and completion notes. Add your information, review the completed document and remove the notes before issue.
The form prepares a separate brief; it does not fill the Word or Excel file.
Read product descriptions in your language. The Word and Excel template files are in English.
Only selected pages are shown. This is not the complete template. The full editable Word or Excel file is supplied with purchase.
Learning
Prepare this plan before changes begin affecting approved project baselines, or when inconsistent requests and approvals show that scope, cost, schedule, and technical decisions need a clearer shared control process.
It establishes how changes are raised, assessed, decided, implemented, and verified, allowing legitimate adjustments to proceed while preserving traceability between the decision, affected baselines, and the work actually delivered.
The project manager typically leads preparation with controls, commercial, engineering, and delivery representatives. Sponsor or governance authorities approve decision rights, while process owners confirm how the plan interfaces with contractual change mechanisms.
Allowing approval of a technical sketch to stand in for all budget and programme decisions leaves the changed baseline and implementation authority ambiguous.
Illustrative example: a logistics project receives frequent tenant layout revisions. The plan establishes who assesses structural, services, cost, and schedule consequences before a decision. An approved loading-area change then updates the relevant drawings and baseline records, while an unapproved office preference remains visibly pending.
Confirm the adopted edition, local amendments, National Annex where relevant, and contract requirements.
Prepare project brief